SCE Santa Clara to Vincent 230 kV

The second leading SB1006 concept, with the same economics argument and the same absence of an approved project.

PURSUE / QUALIFYScore: 83 of 100Confidence: Medium

Evidence chain

  1. 1
    SCE's SB1006 study describes roughly 40 miles of HTLS reconductoring with a 2,180 A emergency rating target on this line.
  2. 2
    Cost escalation and transparency scrutiny apply to this concept as well, and structural modification scope is a primary cost driver.
  3. 3
    Conductor meeting the 2,180 A emergency target with reduced structure modification and shorter outage exposure.
  4. 4
    Yes at the concept stage, with no approved scope to displace.
  5. 5
    Extend the same installed cost and structure modification comparison to this line so both concepts can be addressed together.
  6. 6
    SCE transmission planning and engineering.
  7. 7
    Project advancement, need, and final scope remain open.
  8. 8

Score breakdown

Policy, regulatory or planning trigger17 / 20
Commercial exposure17 / 20
TS technical fit18 / 20
Timing and influenceability10 / 15
Economic, ROW or structure pressure9 / 10
Buyer accessibility4 / 5
Evidence quality8 / 10
83 / 100
SCE | California
PREPARE / QUALIFY
SB1006 planning concept
HTLS assumed in concept, brand open
Installed cost competition against HTLS
Both concepts move through the same planning discussions, so prepare them together.

Required caution

This is a proposal from SCE's SB1006 work, not a confirmed Board approved CAISO project by that name.

Evidence labels

Confirmed factPolicySight assessment

A high score supports commercial diligence. It does not indicate an open procurement or an established supplier decision.