SCE Julian Hinds to Mirage 230 kV

Technically well suited and commercially inactive. A 47 mile HTLS project that CAISO placed on hold after cost escalation.

PROCEDURAL OVERRIDE: DO NOT FORECASTProcedural status overrides the numeric score. Not an active procurement.Score: 77 of 100Confidence: High

Evidence chain

  1. 1
    CAISO documentation describes a 47 mile HTLS reconductoring project and reports cost rising from $76M to $178M, with the project on hold.
  2. 2
    Cost escalation of this size is exactly the condition under which a rescope can revisit conductor and structure assumptions, but only if the project resumes.
  3. 3
    High capacity conductor with favorable weight and sag behavior for long spans and reduced structure modification.
  4. 4
    Not currently. The specification question only reopens if CAISO releases the hold or a rescope is initiated.
  5. 5
    Monitor for release of the hold or a rescope, and hold a cost reduction analysis ready rather than pursuing actively.
  6. 6
    SCE transmission planning and engineering, subject to CAISO status.
  7. 7
    Whether and when the project resumes, and in what form, is unknown.
  8. 8

Score breakdown

Policy, regulatory or planning trigger16 / 20
Commercial exposure17 / 20
TS technical fit18 / 20
Timing and influenceability7 / 15
Economic, ROW or structure pressure9 / 10
Buyer accessibility3 / 5
Evidence quality7 / 10
77 / 100

CAISO placed the project on hold after the estimate rose from $76M to $178M. That procedural status overrides the numeric score of 77. This is not an active procurement and it must not be forecast.

SCE | California
ON HOLD / RE SCOPE WATCH
On hold at CAISO
HTLS scope defined, project paused
Long span HTLS reconductoring
It is not a now opportunity. It is a watch item with a prepared response.

Evidence labels

Confirmed factPolicySight assessment

A high score supports commercial diligence. It does not indicate an open procurement or an established supplier decision.