PG&E Monta Vista to Loyola to Los Altos 60 kV

A 60 kV sub transmission project in a constrained suburban corridor, useful as pipeline breadth rather than a lead pursuit.

QUALIFYScore: 76 of 100Confidence: Medium

Evidence chain

  1. 1
    CAISO approved the Monta Vista to Loyola to Los Altos 60 kV reconductoring project in its 2025 to 2026 transmission plan, with an estimated cost of about $64M. The public conductor type is not specified.
  2. 2
    Suburban corridors limit structure additions, so capacity increase within existing structures is the practical path if loading permits.
  3. 3
    Capacity increase at sub transmission voltage with minimal structural change.
  4. 4
    Possibly. No public conductor type is established, so the specification route runs through PG&E standards and project engineering.
  5. 5
    Qualify required ampacity and structure condition before committing engineering effort.
  6. 6
    PG&E project engineering and transmission standards.
  7. 7
    TS fit depends on the detailed rating and structure constraints, neither of which is public at this stage.
  8. 8

Score breakdown

Policy, regulatory or planning trigger16 / 20
Commercial exposure15 / 20
TS technical fit16 / 20
Timing and influenceability10 / 15
Economic, ROW or structure pressure8 / 10
Buyer accessibility4 / 5
Evidence quality7 / 10
76 / 100
PG&E | California
QUALIFY
Approved in CAISO 2025 to 2026 plan
Public conductor type not specified
Sub transmission capacity increase
Approved and costed at about $64M, so it belongs in the standards case now. Fit still depends on detailed rating and structure constraints.

Evidence labels

Confirmed factPolicySight assessmentUnverified

A high score supports commercial diligence. It does not indicate an open procurement or an established supplier decision.