PG&E Dixon Landing / East San Jose 115 kV rescope

An active engineering effort with a public 3,000 A requirement, a named advanced conductor scope, and no public brand decision.

ACTIVE PURSUITScore: 97 of 100Confidence: High

Evidence chain

  1. 1
    PG&E's Q1 2026 GO 131 E report places the project in engineering and proposes advanced conductors on Piercy to Metcalf, Swift to Metcalf, Newark to Dixon Landing, and McKee to Piercy after large load data centers increased area transmission need.
  2. 2
    The required capability is at least 3,000 A summer emergency across four 115 kV segments, with construction expected to start April 9, 2027 and a CPUC filing anticipated in Q2 2027. Conductor selection, structure loading, and outage sequencing are all still being resolved.
  3. 3
    High ampacity conductor sized to a 3,000 A summer emergency requirement with reduced weight and controlled sag at temperature, limiting structure replacement inside the existing corridor.
  4. 4
    Yes on the engineering question. The conductor family is public and the brand is not, but approved vendor list status is unverified.
  5. 5
    Present a 3,000 A conductor optimization package comparing size, weight, sag temperature behavior, structure loading, hardware changes, outage sequence, installation implications, and total installed cost.
  6. 6
    PG&E transmission engineering, standards, asset management, and procurement.
  7. 7
    Whether PG&E's approved vendor shortlist and standards decision remain open is not established in public evidence.
  8. 8

Score breakdown

Policy, regulatory or planning trigger20 / 20
Commercial exposure20 / 20
TS technical fit20 / 20
Timing and influenceability15 / 15
Economic, ROW or structure pressure10 / 10
Buyer accessibility4 / 5
Evidence quality8 / 10
97 / 100
PG&E | California
ACTIVE / PURSUE
Engineering
Conductor family named, brand open
High ampacity reconductoring in existing structures
Engineering is active now and construction is dated April 9, 2027.

Required caution

Do not imply an open procurement. GO 131 E reporting establishes scope and milestones, not a solicitation.

Evidence labels

Confirmed factPolicySight assessmentUnverified

A high score supports commercial diligence. It does not indicate an open procurement or an established supplier decision.